Larkhill, Farnworth

modular construction company

Client: St Vincents Housing Trust

modular construction company

Scheme Data:
MIX:12 No. 2 bed / 3 person Apartments, 7 No. 3 bed / 5 person Mews properties
JCT: Contract Value: £1.35 million, Contract Period: 52 weeks
BUILD: All units built traditionally to Level 3 of the Code for Sustainable Homes.
Specialist precautions taken for mineshafts, worked seams, knotweed and gassing levels.
All units built on piled foundations and reinforced ring beams.



modular construction company

Green Issues:

GREEN SPACES

  • A newly provided amenity area has been incorporated within the scheme and landscaped with plant species to enhance biodiversity

S.U.D.S

  • On site attenuation installed to restrict surface water run-off into the local sewer system

POWER/HEAT

  • 20% of renewable energy technology installed on roof tops using photo voltaic panels

PLANT LIFE

  • A number of key specimen trees were designated for protection and those have been successfully retained within the development